UAE Supreme Court Rules on Unclear Arbitration Clause

When drafting an arbitration clause, it is vital to make sure that the clauses are simple and clear in order to avoid uncertainty and disputes over their semantics and effect. This is the first step to ensuring the time and cost-effectiveness of a potential dispute as it will minimize the risk of possible disagreements regarding the jurisdiction of the tribunal or the process of appointing the arbitrators. At the very outset of drafting the arbitration clause, it must be explicit that the parties wish to have their disputes resolved via arbitration and to waive the original jurisdiction of the courts. If this intention cannot be inferred, it means that the ‘medium’ used has missed its target.

The repercussions of the failure to express clarity and intention of the parties to refer to arbitration in case of a dispute manifested in a case leading to a Federal Supreme Court judgment issued recently.

The Case in Question

The case in question revolves around an agreement that was executed in March of 2013, relating to the non-payment of medical supplies.

The language used in the arbitration clause was in English and the issue arose out of whether or not the clause was explicit in commanding the parties to refer to arbitration as the dispute resolution mechanism.

The arbitration clause stated in case the parties could not reach an amicable settlement in relation to any dispute within 30 days, either party may trigger arbitration dispute proceedings to be seated in Abu Dhabi, conducted in English and subject to the rules of the Abu Dhabi Commercial Conciliation & Arbitration Centre.

When the dispute arose for non-payment over the sale of the medical supplies, one of the parties filed the dispute before the Primary Court. The Primary Court found it had no jurisdiction to hear the case due to the arbitration clause.

The Primary Court judgement was appealed with the argument that the original language used in the arbitration clause did not obligate the parties to refer to arbitration, but rather, was an optional method for dispute resolution. The Appeals Court accepted the appeal argument and remanded the case to the Primary Court to apply its jurisdiction and rule on the merits of the dispute.

The party arguing that the arbitration clause was obligatory challenged the ruling of the Appeals Court before the Federal Supreme Court on the basis that it had submitted a translation of the arbitration clause from English to Arabic, provided by a judicially certified legal translator, to the court which evidenced that the arbitration clause was obligatory.

The Federal Supreme Court ruled that the judgement of the Appeals Court was unfounded as it did not debunk the translation presented by the party advocating for the obligatory language of the arbitration clause.

The Federal Supreme Court found that the Appeals Court could have ordered the appointment of a language expert from the respective expert registry, or the party advocating for the courts’ jurisdiction could have submitted a counter-translation evidencing that the arbitration clause was indeed optional. Neither of these potential procedures had occurred.

The Federal Supreme Court overturned the Appeals Court judgement.

But what if the Appeals Court of its own accord or by litigant’s request ruled for the requirement of a court-appointed language expert to opine on the English text of the arbitration clause?

Or what if the party advocating for litigation had submitted a translation by a judicially certified translator that arbitration clause was optional?

In both hypotheticals; the result would have been an even further prolongation of the dispute and an increase in costs.

The moral of the case is the importance of clear and effective arbitration clauses (or agreements); that include the seat of arbitration, number and selection of arbitrators, institutional or ad hoc, governing law of the subject matter in dispute and possibly governing law of the arbitration agreement (if different), capacity to agree to arbitration, the authority to sign arbitration agreements, multiple party arbitration, enforcement, opt-in and opt-out provisions (although they may be problematic), sovereign immunity if a party to the transaction is a State, scopes of disputes covered, and other matters.

Author: Mahmoud Abuwasel
Title: Partner – Disputes
Email: mabuwasel@waselandwasel.com
Profile: https://waselandwasel.com/about/mahmoud-abuwasel/
Lawyers and consultants.
Tier-1 services since 1799.
www.waselandwasel.com
business@waselandwasel.com


UAE Supreme Court ruled tender committee liable for contractor’s rejected bids of 65 million Dirhams

 

In the late nineties, a contractor sued a government tender committee for AED 65,467,250 in compensation for losses and lost earnings as a result of not being awarded five tenders related to construction and maintenance works that the contractor had bid for.

The contractor argued that its five bids contained the lowest prices and fulfilled all the conditions of the tenders. Both the primary court and the appeals court rejected the claim.

The Federal Supreme Court, however, overturned the lower court judgments and found the tender committee to be administratively liable towards the contractor for the five rejected bids.

The case was brought forth on grounds of contravening Abu Dhabi Law No. 4/1977 On Tenders, Auctions and Warehouses in the Emirate of Abu Dhabi – particularly on the basis that Article 21 of the said law states that:

“The preference between the tenderers shall be according to the selection of the tenderer presenting the lowest total price, should the bid thereof be consistent with the tender conditions. However, the tenderer presenting a higher price may be chosen should the lower prices be unreasonably low and not assuring proper work progress.”

The Federal Supreme Court ruled that it was evident from the statutes regulating contracting by way of tender, that the legislator has subjected public tenders to basic principles of openness, equality, freedom of competition and the mechanism for awarding the tender, and obligates the administrative authority (i.e. the tender committee) to disclose the reasons for rejection of a bid.

The Court’s rationale was that this is to ensure that the administrative authority follows a decreed path in order to reach the appointment of the best bidders in accordance with the law. The contracting procedures are organized by way of tender, so that it takes place in two stages, the first of which includes preliminary work and the second in which the contract is concluded.

Continuing, the Court stated that the preliminary tender processes consist of setting the conditions for the tender, announcing it, receiving bids, fulfilling the conditions of the tender, and then separating between the bids. These were considered by the Court to be internal organizational rules that are the prerogative of the tender committee. Nonetheless, the Court opined that the provisions that are set by the legislator are for the benefit of the administrative authority (i.e. the tender committee) and private persons alike, with the aim of ensuring the impartiality of the bidding processes and respecting the principle of equality among all bidders.

In interpreting the law, the Federal Supreme Court noted that the bidder with the lowest price is originally the owner of the right to the award whenever the bid is consistent with the terms of the tender, and with the exception of this principle, the administrative authority may award the tender that was submitted at a higher price if the lower price was unreasonably reduced, as there may be concerns regarding good performance, and this exception was a violation of the basic principle that governs public tendering procedures, which is the mechanism for awarding the tender.

In its judgment, the Federal Supreme Court found the tender committee to be administratively liable.

The significance of this case is not only that a contractor had succeeded in an action against an administrative decision issued by an administrative authority (i.e. the tender committee), but that the Federal Supreme Court found the committee to be liable for its decision.

In other words, the Court did not only invalidate the decision, but also found that liability arose against the contractor’s claim of AED 65,467,250.

One of the rarely commented upon competencies under Emirati law is administrative law and administrative decisions; the law that governs the relations between government agencies, and government agencies and the private sector, and the decision taken by government agencies.

There is no single administrative legislative text in the UAE, rather, the corpus of administrative law is comprised of scattered provisions in various pieces of legislation – but mainly the Constitution and Article 84 (bis) of the Civil Procedures Law – and also scholarly works and jurisprudence.

As a matter of fact, Article 84 (bis) was only added to the Civil Procedures Law in 2014.

In 2019, there were almost 1,130 administrative cases filed before the various stages of the Federal Courts. Not to mention the myriad other administrative cases that are domestic respective of domestic administrative authorities in Emirates that have independent judicial authorities (i.e. Abu Dhabi, Dubai, RAKI, DIFC, and ADGM).

Most administrative disputes revolve around invalidating an administrative decision – in other words – cancelling the administrative decision and its consequence. The discussion surrounding forms and procedures of administrative disputes is quite broad and has its own respective nuances such as the effects of administrative decision in rem and those in personam, and whether effects can be retrospective, or whether there can be a monetary value attached to an administrative decision and its invalidation.

However, with all that said, it is extremely rare for a Court to find an administrative authority liable for an administrative decision – particularly where the plaintiff is claiming compensation for losses and lost earnings.

Generally, the Courts either uphold the administrative decision, or invalidate it, or invalidate it and replace it with a quasi-judicial/administrative decision – but rarely does a Court find the administrative authority liable.

This particular case in this article is what one may refer to as an ‘orphan’ case. It occurred in an exceptional instance, and it is unclear if there are other similar judgments, or whether the Federal Supreme Court may repeat such a judgment.

Author: Mahmoud Abuwasel
Title: Partner – Disputes
Email: mabuwasel@waselandwasel.com
Profile: https://waselandwasel.com/about/mahmoud-abuwasel/
Lawyers and consultants.
Tier-1 services since 1799.
www.waselandwasel.com
business@waselandwasel.com