Construction on Dubai’s Azizi Plaza residential project reaches 90%

Construction on UAE-based Azizi Developments’ 434-unit residential Plaza complex has reached 90% completion and is on track to be delivered by Q2 2020.

The development, which comprises 286 studios, 46 one-bedroom units, 86 two-bedroom residences, and 16 penthouses, is located within Dubai’s Al Furjan area.

In terms of construction, Plaza’s structure is 100% complete, while both the blockwork and internal plaster are at 99%.

The building’s tiling stands at 98% and both heating, ventilation, and air conditioning (HVAC) and the second mechanical, electrical and plumbing (MEP) fix have recorded 91%.

Progress on the external works is on schedule as well — currently at 42%, with the swimming pool having reached 81%. Overall finishing works are at 88%, while the façade and elevator works have reached 90 and 92% respectively.

Commenting on the construction progress, Azizi Developments executive director for its Engineering Division, Mohammed Ragheb, said: “Plaza constitutes 434 units of the approximately 3,000 homes that we are well on track to deliver this year.”

He added: “With the remarkably swift material sourcing and increased workforce, we are confident that we will complete this impressive, sizable project within a few months, in the second quarter of 2020.”