VIDEO: Construction update on Oman’s Duqm Refinery project

Oman’s Duqm Refinery project has recorded 55.2% overall progress as of March 2020. 

The project progress so far includes 2,92,591m3 of concrete poured; 2,034 civil piles driven; 22,455.5 tonnes of structural steel usage; installation of a 95,843m pipe, and 35,579.7 tonnes of tanks used. 

The project has recorded 21,206 manpower on-site so far, achieving a total of 43 million safe manhours. 

Recently, Oman’s Port of Duqm, which is facilitating the construction for Duqm Refinery, received the SAL Heavy Lift vessel M.V.Anne Sofie for its project, marking a milestone in heavy lift cargo operation. 